The following timeline contains estimated dates for completing portions of the construction project. These dates can change due to unpredicted circumstances.
- June 30, 2010 - Official Groundbreaking Ceremony (click here to see pictures of the event)
- July 5, 2010 - Construction officially begins. Excavating of foundation begins.
- Early August 2010 - Foundation pad is formed. Portions of foundation must set for 45 days.
- Mid-August 2010 - Footings being dug and poured on some portions of foundation; Excavating of main driveway begins; Outside sewer and drainage lines to be installed.
- Late August 2010 - Final foundation footings to be dug and poured.
- Early September 2010 - Pre-cast walls scheduled to arrive.
- Late September 2010 - Walls to be erected.
- October to Mid-December 2010 - Roof installed.
- December 2010-December 2011 - Interior work.
- January 2012 - Completion of new hospital
- Mid-January 2012 - MOVE-IN/OPEN NEW FACILITY
